Construction Update - December 2021

Dec 17, 2021

The team is busy constructing your new home. See the completed, new and upcoming milestones for the month.

It’s beginning to feel like HOME, with structural topping out complete. This means that the building’s roof is in place - representing a key milestone in the construction process.

Installation of hydraulic services is complete from the basement to level ten, along with all mechanical and electrical services installed across the basement to level eight.

On the outside, facade works on level one have been finalised, and the wall set out finished from the ground level to level ten.

Level four common area planters are complete, with interior joinery commencing and finishing trades now onsite