Construction Update - February 2022

Feb 18, 2022

The team is busy constructing your new home. See the completed, new and upcoming milestones for the month.

Interior work is ramping up, with great progress made across all painting, joinery, flooring, tiling and waterproofing works. We should see an increase of interior work completed across the next few months, with the builder’s lift to be installed by the middle of February – which will allow faster access to the upper levels.

Installation of wiring and fire services continues from level 11, with the facade window wall and curtain wall across levels 13 and 14 commencing. 

Interior partitions are completed to level five, along with flooring and joinery installed up to level four. Tiling is being finalised on level three, with final paint work and carpeting completed to level two.

Brickwork detailing is nearly finalised on the north elevation, with blockwork, painting, and waterproofing making progress across level four.