Construction Update - January 2022

Jan 21, 2022

The team is busy constructing your new home. See the completed, new and upcoming milestones for the month.

With the major construction milestone of topping out (the construction of the roof) completed in 2021, focus has now shifted to interior works.

Installation of wiring and fire services continue upwards from level 11, with interior works including painting, caulking, and joinery being installed from levels four to six.

The common areas are taking shape, with block work commencing, additional planters added, level 16 pool works beginning, and artwork being installed in the podium shortly. 

The final clean and builder’s inspections have commenced across levels one and two, with the Terrace Homes fully constructed. Permanent power to the site is expected in early February.