Construction Update - May 2022

May 20, 2022

The team is busy constructing your new home. See the completed, new and upcoming milestones for the month.

Construction on HOME is nearing completion with the installation of the building’s services. These being fire, hydraulics, mechanical, fire penetrations, and electrical rough-in coming to completion for almost all serviced apartments. Level seven is the exception as fire, hydraulics, mechanical and electrical remain in the fit-off stage. Level 13 is also nearing the completion of the fire fit-off stage as well.

Flooring installations have also finished on level nine. Meanwhile down on level eight, appliances are in the fit-off stage, with carpeting being laid on level six.

Works on the pergolas and steel structures are presently underway. The walls of the communal lounge and dining areas have been painted. Artwork installations on levels 14 and 16 have been given the thumbs up and are being displayed proudly.

Outside of the building, work has commenced on Nelmore Lane. Contractor coordinating works are also required on civil footpath works for both the Heidelberg and Chandler highways.

A detailed defect program is currently being worked on for all common areas. With the commencement of level four and level six defecting process happening concurrently.

HOME is still on track for settlement in Spring 2022. We will keep you posted with any specific updates regarding the settlement process and key dates soon.